Building Permit Timelines by City in Central Florida
Which office permits a new home in each city we build in, and how long it takes.
A new single-family home in Central Florida is permitted by the city if the lot sits inside city limits, and by the county if it does not. Across the 31 cities Brightview builds in, permitting takes 6–12 weeks from application to issued permit, and construction runs 7–9 months after that.
Who permits your home, by city
The office named here is the one that reviews a new single-family home on a lot inside that city. A parcel with the same mailing address but outside city limits is permitted by the county instead — the parcel decides it, not the address.
| City | County | Permitted through | Typical permit window |
|---|---|---|---|
| Melbourne | Brevard County | City of Melbourne Building Department | 6–12 weeks * |
| Palm Bay | Brevard County | City of Palm Bay Building Division | 6–12 weeks * |
| Titusville | Brevard County | City of Titusville Building Department | 6–12 weeks * |
| Palm Coast | Flagler County | City of Palm Coast Building Division | 6–12 weeks * |
| Clermont | Lake County | City of Clermont Building Services | 6–12 weeks * |
| Eustis | Lake County | City of Eustis Building Department | 6–12 weeks * |
| Groveland | Lake County | City of Groveland Building Department | 6–12 weeks * |
| Leesburg | Lake County | City of Leesburg Building Department | 6–12 weeks * |
| Mount Dora | Lake County | City of Mount Dora Building Department | 6–12 weeks * |
| Apopka | Orange County | City of Apopka Community Development Department | 6–12 weeks |
| Ocoee | Orange County | City of Ocoee Building Department | 6–12 weeks * |
| Orlando | Orange County | City of Orlando Permitting Services | 6–12 weeks * |
| Winter Garden | Orange County | City of Winter Garden Building Department | 6–12 weeks * |
| Winter Park | Orange County | the City of Winter Park's Code Enforcement & Permitting Services | 8–14 weeks |
| Celebration | Osceola County | Osceola County Development Review | 6–12 weeks * |
| Kissimmee | Osceola County | City of Kissimmee Building Division | 6–12 weeks * |
| Poinciana | Osceola County | Osceola County Development Review | 6–12 weeks * |
| St. Cloud | Osceola County | City of St. Cloud Building Department | 6–12 weeks * |
| Davenport | Polk County | City of Davenport Building Department | 6–12 weeks * |
| Haines City | Polk County | City of Haines City Building Department | 6–12 weeks * |
| Lakeland | Polk County | City of Lakeland Building Inspection Division | 6–12 weeks * |
| Winter Haven | Polk County | City of Winter Haven Building Department | 6–12 weeks * |
| Lake Mary | Seminole County | City of Lake Mary Building Department | 6–10 weeks |
| Longwood | Seminole County | City of Longwood Building Department | 6–12 weeks * |
| Oviedo | Seminole County | City of Oviedo Development Services Department | 6–10 weeks |
| Sanford | Seminole County | City of Sanford Building Department | 6–10 weeks |
| Daytona Beach | Volusia County | City of Daytona Beach Building Division | 6–12 weeks * |
| DeLand | Volusia County | City of DeLand Building Department | 6–12 weeks * |
| Deltona | Volusia County | City of Deltona Building Department | 6–12 weeks * |
| New Smyrna Beach | Volusia County | City of New Smyrna Beach Building Department | 6–12 weeks * |
| Port Orange | Volusia County | City of Port Orange Building Department | 6–12 weeks * |
Last updated 2026-09-02. Windows marked * are the 6–12 week range Brightview sees across that county; the other 5 are windows we track for that city specifically. These are our own build experience, not a published municipal service standard, and they exclude time spent in revisions. Fee schedules and review queues change.
Why one city takes longer than another
- Design review. Winter Park reviews new construction and accessory structures for architectural compatibility, which adds weeks a neighbouring city does not.
- HOA architectural review. Where a subdivision has one, it runs before the city will accept the permit application — typically another 2–4 weeks.
- Septic vs sewer. A septic parcel adds a county health department review that a sewered lot never sees.
- Flood and coastal. Near-coast parcels in Volusia, Brevard and Flagler carry wind-load and sometimes flood-zone review on top of the standard set.
- Unincorporated parcels. County review is often faster than a city’s, but the impact fees are the same and HOA covenants still apply.
Permit questions
Who issues the building permit for a new home in Central Florida?+
The city, if the lot sits inside city limits, and the county if it does not. A Deltona address is permitted by the City of Deltona Building Department; an unincorporated Volusia address goes to Volusia County Building & Zoning. The mailing address does not decide it — the parcel does.
How long does a new-home building permit take in Central Florida?+
Typically 6–12 weeks from application to issued permit across the eight counties Brightview builds in. Winter Park runs longer, 8–14 weeks, because accessory and new-construction plans go through design review. Lake Mary, Oviedo and Sanford typically run 6–10 weeks.
How long does the house take to build once the permit is issued?+
Roughly 7–9 months of construction for a production plan. Lot work — clearing, fill, septic or utility taps — can add time on an unimproved parcel, which is why Brightview quotes it separately rather than averaging it into the plan price.
Do I have to pull the permit myself?+
No. Brightview files the application, pays the impact and tap fees, and carries every inspection through certificate of occupancy.
Are impact fees included in the price?+
Yes. Every plan price Brightview publishes includes that county's impact and tap fees, which is not the industry norm — most builders quote a base price and bill fees separately at permit. See the cost-to-build page for the county-by-county breakdown.
Send us the address, we’ll tell you who permits it
A free written feasibility check: jurisdiction, zoning, setbacks, utilities and what it will take to build there.