How to demolish a house in Longwood, FL
In Longwood, residential demolition permits are issued by the City of Longwood Building Division (application: Demolition Permit Application with Demolition Permit Procedures (version October 2022)). If the house is a designated landmark or sits in a local historic district, review by the City Commission (no separate historic board found; Community Development Department reviews) comes first.

Demolition permit steps in Longwood
Step 1
Optional pre-permit meeting with the Building Official.
Step 2
Submit the application with all attachments and utility shut-off confirmations.
Step 3
Install silt fence, inlet protection and turbidity barriers; city staff inspect and sign off.
Step 4
Install right-of-way and pedestrian protection; city staff inspect and sign off.
Step 5
Pre-issuance inspection verifies utilities disconnected, runoff controls, fencing and ROW protection.
Step 6
Permit released; schedule an in-progress inspection the day work starts.
Step 7
Final inspection after debris removal and site restoration.
Documents Longwood asks for
| Document | What it is |
|---|---|
| Notarized owner letter | Acknowledges the structure will be demolished and the property is vacant. [1] |
| Written description of demolition methods and debris storage | [1] |
| Written description of materials removed and disposal (recycle, landfill, hazardous waste) | [1] |
| Erosion, runoff, dust and debris control plan | [1] |
| Site plan or survey | Shows improvements to be removed and to remain. [1] |
| Utility disconnect letters | Including the Seminole County Health Department for septic systems. [1] |
| Licensed mechanical or A/C contractor in the permit package | For refrigerant removal; affidavit of refrigerant removed at final. [1] |
| Asbestos documentation | Copy of the required notification and contact with the State Asbestos Coordinator. [1] |
| Notice of Commencement | When required by Chapter 713, F.S. [1] |
If the house is historic in Longwood
Who reviews it: City Commission (no separate historic board found; Community Development Department reviews).
When it applies
- Contributing structure in the Longwood Historic District shown on the future land use map (LDC s. 10.7.0).
How the review works
- Applicant must show demolition is warranted and that alternatives including renovation, stabilization or relocation were explored; demolition approval must be final before the building permit for demolition issues (s. 10.7.1.C.2).
- Application to Community Development, which prepares findings for the City Commission (s. 10.7.1.C.4).
- Notice mailed to all property owners in the district, newspaper or website publication, and site posting (s. 10.7.3).
- City Commission hearing; the Commission has up to 270 calendar days to decide and may postpone to save the structure (s. 10.7.1.C.5).
- Demolition only to clear land or avoid maintenance is not an option; without a defined redevelopment plan, the only reason to demolish a contributing structure is an imminent threat to health or safety (s. 10.7.1.C.1).
What the board can ask for
- Evidence of good-faith efforts to pursue alternatives, including offering the property for sale or moving it within the district (s. 10.7.1.C.3).
- Pictures of the building and land from the front street (s. 10.7.1.C.3(f)(xiii)).
- Pictures of all exterior elevations from rooftop to ground and of interior rooms (s. 10.7.1.C.3(f)(xiv)).
- A statement of all special features and materials used inside and outside (s. 10.7.1.C.3(f)(xv)).
- Cost estimates, engineer or architect report on structural soundness and suitability for rehabilitation, market values, purchase details, mortgage, appraisals, listings, assessed values, taxes, form of ownership (s. 10.7.1.C.3(f)).
- City may hire a licensed architect specializing in historic structures to evaluate submittals at the applicant's cost†.
Demolition delay: City Commission has up to 270 calendar days to decide and may postpone further (s. 10.7.1.C.5).
Relocation, salvage and donation: Alternatives must include relocation; economic hardship requires showing the owner tried feasible alternatives such as offering the resource for sale or moving it elsewhere in the district (s. 10.7.1.C).
Sources: [2]
Utilities, asbestos, septic and trees in Longwood
The office that issues it
State rules apply on top of the local ones
The asbestos notice, septic and well abandonment, owner-builder limits and the Notice of Commencement come from state law. See the Florida rules that apply to every demolition.
Straight answers
Do I need a permit to demolish a house in Longwood?
Yes. Residential demolition in Longwood is permitted through the City of Longwood Building Division.
Who can pull a demolition permit in Longwood?
One or two-family homes: an owner-builder (subject to Building Code exemption standards) or a state-licensed residential contractor. Other buildings: Division 1 contractor or licensed demolition specialty contractor. Proof of liability and workers' comp insurance.
What if my house is historic in Longwood?
If the house is a local landmark or in a local historic district, City Commission (no separate historic board found; Community Development Department reviews) reviews the demolition before a permit can issue. City Commission has up to 270 calendar days to decide and may postpone further (s. 10.7.1.C.5).
Do I need an asbestos survey to demolish a house in Longwood?
Longwood lists the State Asbestos Coordinator at 407-897-4100 and DEP notification at 850-717-9000. FDEP Notice of Renovation or Demolition (Form 62-257.900(1)) at least 10 working days before demolition for buildings subject to the asbestos NESHAP; isolated residential buildings of four or fewer units are generally exempt unless part of a larger project or used commercially. FDEP Central District: 407-897-4100. see the Florida rules on our residential demolition page.
Can Brightview handle the demolition in Longwood?
Yes. Brightview Homes (CRC1334100) pulls the permit under its Florida contractor license and runs the asbestos survey and notice, utility disconnects, historic documentation when it applies, tear-down, haul-off and final inspection. Demolition is quoted per job, typically $12,000 to $24,000.
Where this comes from
Every fact on this page comes from the official sources below, read on the date shown. Rules change; the building department has the final word.
- City of Longwood Demolition Permit Procedures, version October 2022
https://www.longwoodfl.org/DocumentCenter/View/8597/Demolition-Permit-Requirements-PDF - Longwood Development Code s. 10.7.0 Historic district
https://library.municode.com/fl/longwood/codes/code_of_ordinances?nodeId=PTIIILODECO_ARTXAD_10.7.0HIDI - https://www.longwoodfl.org/DocumentCenter/View/4597/Demolition-Permit-Application-PDF-
https://www.longwoodfl.org/DocumentCenter/View/4597/Demolition-Permit-Application-PDF- - https://www.longwoodfl.org/169/Building-Division
https://www.longwoodfl.org/169/Building-Division
What we could not confirm in published sources
Ask the building department about these before you plan around them.
- Historic district demolition application fee (Code s. 2-424 lists one; amount not read).
- Building Division address.
- Whether the Historic District Code Book adds requirements.
Get this scope quoted in Seminole County
Send the address or parcel ID. A real person replies within one business day with a written proposal. Nothing is ordered and nothing is charged until you approve it.
Prefer Spanish? Our team works with you in English or Spanish, from the county board to the permit counter.
- Residential Demolition