How to demolish a house in Melbourne, FL
In Melbourne, residential demolition permits are issued by the City of Melbourne Building Section (application: Demolition (EnerGov permit type)). If the house is a designated landmark or sits in a local historic district, review by the Historic and Architectural Review Board (HARB); Historic Preservation Officer approves some CoAs comes first.

Demolition permit steps in Melbourne
Step 1
If the property is a locally designated historic resource or in the Eau Gallie Historic District, contact Community Development (321-608-7500) about a Certificate of Appropriateness before applying.
Step 2
Apply in EnerGov under the demolition permit type.
Step 3
Upload a survey (the Document Submittal Guide lists 1 PDF SURVEY for DEMOLITION). Uploaded documents must be digitally signed and sealed where required, unlocked and named by content.
Step 4
Schedule required inspections through the contractor portal.
If the house is historic in Melbourne
Who reviews it: Historic and Architectural Review Board (HARB); Historic Preservation Officer approves some CoAs.
When it applies
- Property listed on the Melbourne Register of Historic Places (locally designated by City Council resolution).
- Contributing resource in the Eau Gallie Historic District (12 contributing resources listed by the city).
- Designation eligibility requires at least 50 years of age and other criteria in City Code Chapter 20, Article VIII, Sec. 20-266; all owners must consent to a designation petition.
How the review works
- A Certificate of Appropriateness is required for exterior changes to designated properties that need a building permit, before the permit is issued.
- The HPO or HARB approves the CoA depending on the type of work; work inconsistent with the Secretary of the Interior's Standards for Rehabilitation is not permitted.
- There is no fee for a CoA. Apply through Community Development (community.development@mlbfl.org, 321-608-7500).
- HARB meets the third Wednesday of each month at 6 p.m. in the City Hall Council Chamber.
Utilities, asbestos, septic and trees in Melbourne
The office that issues it
State rules apply on top of the local ones
The asbestos notice, septic and well abandonment, owner-builder limits and the Notice of Commencement come from state law. See the Florida rules that apply to every demolition.
Straight answers
Do I need a permit to demolish a house in Melbourne?
Yes. Residential demolition in Melbourne is permitted through the City of Melbourne Building Section. Fee: Valuation based. Demolition of structure is a construction-related permit under the fee schedule effective August 7, 2026: $65.00 for $1,000 or less; $65.00 plus $6.50 per additional $1,000 up to $50,000; $383.50 plus $5.50 per $1,000 up to $100,000; $653.00 plus $4.50 per $1,000 up to $500,000. Plan check is 50% of the base fee, a 5% technology fee applies to all Building Division fees, and Community Development and Engineering review is $25.00 per department per permit. Work started without a permit doubles all fees..
Who can pull a demolition permit in Melbourne?
Licensed contractor, or an owner-builder for residential work only when the property is for the owner's own occupancy and not offered for sale or lease; the owner-builder affidavit is notarized and completed in person (per the city's owner-builder guidance and FAQ).
What if my house is historic in Melbourne?
If the house is a local landmark or in a local historic district, Historic and Architectural Review Board (HARB); Historic Preservation Officer approves some CoAs reviews the demolition before a permit can issue.
Do I need an asbestos survey to demolish a house in Melbourne?
No local asbestos program covers this county; FDEP Central District (main line 407-897-4100) receives the Notice of Renovation or Demolition (DEP Form 62-257.900(1), Notice of Demolition or Asbestos Renovation) at least 10 working days before the project start date for projects removing asbestos above the NESHAP thresholds. FDEP lists a $200 flat fee for hard copy or Pay Later notices and a $100 fee when paid through the DEP Business Portal Pay Now feature (effective March 23, 2025). FDEP says buildings meeting the residential exemption criteria in the Asbestos NESHAP are excluded from the work practice requirements; check 40 CFR Part 61 Subpart M for whether a given house qualifies.
Can Brightview handle the demolition in Melbourne?
Yes. Brightview Homes (CRC1334100) pulls the permit under its Florida contractor license and runs the asbestos survey and notice, utility disconnects, historic documentation when it applies, tear-down, haul-off and final inspection. Demolition is quoted per job, typically $12,000 to $24,000.
Where this comes from
Every fact on this page comes from the official sources below, read on the date shown. Rules change; the building department has the final word.
- Melbourne Building Section
https://www.melbourneflorida.org/Government/Departments/Code-Compliance-Division/Building-Section - Melbourne Building Permit Fees effective August 7, 2026
https://www.melbourneflorida.org/files/assets/public/v/2/code-compliance/building-section/080726-building-permit-fees.pdf - Melbourne EnerGov Submittal Clarifications and Document Submittal Guide (January 2021)
https://www.melbourneflorida.org/files/assets/public/v/1/code-compliance/building-section/january-2021-energov-submittal-clarifications.pdf - Melbourne Building Section FAQ †
https://www.melbourneflorida.org/Government/Departments/Code-Compliance-Division/Building-Section/Frequently-Asked-Questions - Owner Builders in the City of Melbourne †
https://www.melbourneflorida.org/files/assets/public/v/2/code-compliance/building-section/owner-builder-updated.pdf - Melbourne Historic Preservation
https://www.melbourneflorida.org/Government/Departments/Community-Development/Historic-Preservation - Melbourne Historic and Architectural Review Board
https://www.melbourneflorida.org/Government/Municipal-Boards/Historic-Architectural-Review-Board - FDEP Asbestos program page (Central District coverage, 10 working day notice, fees)
https://floridadep.gov/air/permitting-compliance/content/asbestos - FDEP Onsite Sewage FAQ, Permitting (which counties DOH still permits)
https://floridadep.gov/water/onsite-sewage/content/onsite-sewage-faq-permitting - DOH Brevard OSTDS Application Packet for Repair Permits and Abandonments (Rev 08/26)
https://brevard.floridahealth.gov/wp-content/uploads/sites/8/2025/04/repairs-and-tank-abandonments.pdf - FDEP Permitting of ENR-OSTDS, Indian River Lagoon Protection Program
https://floridadep.gov/water/onsite-sewage/content/permitting-enhanced-nutrient-reducing-onsite-sewage-treatment-and - https://energovweb25.mlbfl.org/energov_prod/selfservice/#/home
https://energovweb25.mlbfl.org/energov_prod/selfservice/#/home - https://brevard.floridahealth.gov/wp-content/uploads/sites/8/2025/04/repairs-and-tank-abandonments.pdf ; https://floridadep.gov/water/onsite-sewage/content/onsite-sewage-faq-permitting ; https://floridadep.gov/water/onsite-sewage/content/permitting-enhanced-nutrient-reducing-onsite-sewage-treatment-and
https://brevard.floridahealth.gov/wp-content/uploads/sites/8/2025/04/repairs-and-tank-abandonments.pdf ; https://floridadep.gov/water/onsite-sewage/content/onsite-sewage-faq-permitting ; https://floridadep.gov/water/onsite-sewage/content/permitting-enhanced-nutrient-reducing-onsite-sewage-treatment-and
† Read from a search engine's copy of the official page because the government site blocked direct access during our research. Treat these items as unconfirmed and check them with the office.
What we could not confirm in published sources
Ask the building department about these before you plan around them.
- Whether demolition of a designated property needs HARB (board) review or HPO (staff) review, and what Chapter 20, Article VIII says on demolition criteria, delay, documentation, relocation or salvage.
- Whether Melbourne requires utility disconnect letters before a demolition permit issues.
- Melbourne tree removal permit rules for demolition sites.
- Average review time specific to demolition permits.
Get this scope quoted in Brevard County
Send the address or parcel ID. A real person replies within one business day with a written proposal. Nothing is ordered and nothing is charged until you approve it.
Prefer Spanish? Our team works with you in English or Spanish, from the county board to the permit counter.
- Residential Demolition