How to demolish a house in Lakeland, FL

In Lakeland, residential demolition permits are issued by the City of Lakeland Building Inspection Division (application: Demolition permit application in iMS). If the house is a designated landmark or sits in a local historic district, review by the Historic Preservation Board and its Design Review Committee comes first.

Verified 2026-10-12 from 8 official sourcesHistoric review applies to some houses
Residential lot
CRC13341008 Central Florida counties480 N Orlando Ave, Suite 236, Winter Park, FL 32789(407) 543-1739
The process

Demolition permit steps in Lakeland

  1. Step 1

    If the house is in a historic district or is a historic landmark, obtain a Certificate of Review (Design Review, Major) first; it must be granted before building and demolition permits issue.

  2. Step 2

    Have a plumbing contractor cap the sewer; the sewer cap permit must be issued, inspected and finaled before the demolition application is submitted.

  3. Step 3

    If there is a septic tank, get an abandonment letter from the Polk County Health Department (or a pump and inspection report if the tank will be reused).

  4. Step 4

    Upload to iMS: notarized signed owner letter authorizing demolition, recorded Notice of Commencement if the job is over $5,000, septic letter if applicable.

  5. Step 5

    Asbestos removal, if required, by an Asbestos Abatement Contractor only; notify the Building Inspection Division.

  6. Step 6

    Schedule the Public Works Engineering pre-demolition site inspection (existing erosion, driveway aprons, sidewalks, right of way items) in advance.

  7. Step 7

    Demolish, level and grade the site, remove all debris.

  8. Step 8

    Final inspections by the Building Division and by Public Works.

What to submit

Documents Lakeland asks for

DocumentWhat it is
Notarized owner authorization letterA notarized, signed letter from the property owner authorizing the demolition. [1]
Recorded Notice of CommencementIf job valuation or contract amount is over $5,000. [1]
Septic tank abandonment letterFrom the Polk County Health Department; a pump and inspection report instead if the tank will be reused. [1]
Finaled sewer cap permitMust be issued, inspected and finaled before the demolition application. [1]
Historic houses

If the house is historic in Lakeland

Who reviews it: Historic Preservation Board and its Design Review Committee.

When it applies

  • Principal or accessory building within one of seven local historic districts: Beacon Hill, Biltmore-Cumberland, Dixieland, East Lake Morton, Lake Hunter Terrace, Munn Park, South Lake Morton.
  • Local Historic Landmark anywhere in the city.

How the review works

  • Demolition of a principal structure in a historic district requires Design Review (Major) and a Certificate of Review; accessory buildings require Design Review (Minor) and a Certificate of Review.
  • Apply through iMS; the Historic Preservation Planner reviews first and the Design Review Committee makes the final decision on Major reviews. The applicant or a representative must attend.
  • Design Review Committee meets the fourth Thursday of each month at 8:30 AM at City Hall (third Thursday in November and December).
  • Typical Major review about 30 days (FAQ) or about 24 days average (Design Review page).
  • Application fee $170.00 for all demolitions; work done without a Certificate of Review incurs a $350.00 penalty fee.
  • The Certificate of Review must be granted before building and demolition permits are issued.
  • Demolition criteria for principal structures are in LDC Article 11, Section 11.6.3.c (per city FAQ).

Historic district map and list

Sources: [2], [3], [7]

Before the machine shows up

Utilities, asbestos, septic and trees in Lakeland

Utilities
  • Sewer (plumbing contractor): Sewer must be capped by a plumbing contractor under a finaled sewer cap permit before the demolition application. [1]
  • Lakeland Electric: County demolition specifications state that for properties within Lakeland city limits Lakeland Electric is notified to disconnect the power source. [6]
Asbestos

FDEP; Asbestos Abatement Contractor: Asbestos removal (if required) is done by an Asbestos Abatement Contractor only, and the Building Inspection Division must be notified of the scheduled demolition. [1]

Septic and well

Florida Department of Health in Polk County: Septic tank abandonment letter from the Polk County Health Department uploaded with the application, or pump and inspection report if the tank will be reused. [1]

After the house is down
  • Building Division final inspection once the building is demolished and removed and the site is leveled, graded and cleared of all debris.
  • Public Works final inspection of site condition for new damage and cleanup, including erosion control, vegetation or dust control, and barricaded driveways.
Good to know
  • Inspections can be scheduled in iMS, by IVR at 863-226-1519, or by text at 877-667-1720.
  • Historic Preservation Planner: 863-834-6011, historicpreservation@lakelandgov.net.
  • Florida Southern College main campus is a separate National Register Landmark District.
Where to file

The office that issues it

City of Lakeland Building Inspection Division (Community and Economic Development)

City Hall, 228 S. Massachusetts Ave., Lakeland, FL 33801

863-834-6012

Department website

iMS

Demolition application

Who may apply: Demolition contractor, or owner-builder (city posts an Owner-Builder Packet).

Florida rules

State rules apply on top of the local ones

The asbestos notice, septic and well abandonment, owner-builder limits and the Notice of Commencement come from state law. See the Florida rules that apply to every demolition.

Questions people actually ask

Straight answers

Do I need a permit to demolish a house in Lakeland?

Yes. Residential demolition in Lakeland is permitted through the City of Lakeland Building Inspection Division.

Who can pull a demolition permit in Lakeland?

Demolition contractor, or owner-builder (city posts an Owner-Builder Packet).

What if my house is historic in Lakeland?

If the house is a local landmark or in a local historic district, Historic Preservation Board and its Design Review Committee reviews the demolition before a permit can issue.

Do I need an asbestos survey to demolish a house in Lakeland?

Asbestos removal (if required) is done by an Asbestos Abatement Contractor only, and the Building Inspection Division must be notified of the scheduled demolition.

Can Brightview handle the demolition in Lakeland?

Yes. Brightview Homes (CRC1334100) pulls the permit under its Florida contractor license and runs the asbestos survey and notice, utility disconnects, historic documentation when it applies, tear-down, haul-off and final inspection. Demolition is quoted per job, typically $12,000 to $24,000.

Sources · verified 2026-10-12

Where this comes from

Every fact on this page comes from the official sources below, read on the date shown. Rules change; the building department has the final word.

  1. Lakeland Building Inspection Forms and Checklists (demolition permit summary)
    https://www.lakelandgov.net/departments/community-economic-development/building-inspection/forms-checklists/
  2. Lakeland Historic Preservation FAQ
    https://lakelandgov.net/departments/community-economic-development/historic-preservation/frequently-asked-questions/
  3. Lakeland Historic Preservation Design Review
    https://www.lakelandgov.net/departments/community-economic-development/historic-preservation/design-review/
  4. Lakeland Owner-Builder Packet (link only, not read)
    https://lakelandgov.net/media/23453/owner-builder-package.pdf
  5. https://ims.lakelandgov.net/ims/Account/Login
    https://ims.lakelandgov.net/ims/Account/Login
  6. https://www.polkfl.gov/wp-content/uploads/2026/02/DQ-26-176-Quote-Package.pdf
    https://www.polkfl.gov/wp-content/uploads/2026/02/DQ-26-176-Quote-Package.pdf
  7. https://lakelandgov.net/media/6696/lakeland-historic-districts-2017.pdf
    https://lakelandgov.net/media/6696/lakeland-historic-districts-2017.pdf
  8. https://www.lakelandgov.net/departments/community-economic-development/building-inspection/
    https://www.lakelandgov.net/departments/community-economic-development/building-inspection/

What we could not confirm in published sources

Ask the building department about these before you plan around them.

  • The official LDC Article 11 text (Municode) could not be loaded. A third-party mirror (zoneomics) shows demolition criteria at 11.6.3(d) (architectural significance, contribution to the district, future use of the site) and relocation at 11.6.3(c), while the city FAQ says demolition criteria are at 11.6.3.c.
  • The same mirror shows 11.6.4(a) allowing a demolition permit only after the building permit for the replacement structure is issued (with exceptions). Not verified on an official source; this would be a major requirement if confirmed.
  • Required documentation for a demolition Certificate of Review (photos, structural report, etc.) not listed on pages read; the Design Guidelines PDF was too large to fetch.
  • Demolition building permit fee not found.
  • The older demolition-permits PDF at lakelandgov.net/media/20275 now returns not found.
Start here

Get this scope quoted in Polk County

Send the address or parcel ID. A real person replies within one business day with a written proposal. Nothing is ordered and nothing is charged until you approve it.

Prefer Spanish? Our team works with you in English or Spanish, from the county board to the permit counter.

Selected scope
  • Residential Demolition
What is the plan? *