How to demolish a house in Daytona Beach, FL
In Daytona Beach, residential demolition permits are issued by the City of Daytona Beach (Site Demolition and Restoration Permit under LDC Sec. 3.4.O plus demolition building permit) (application: Demolition Permit Package: Demolition Permit Submittal Checklist, Demolition Permit Application, Notice of City Utilities Removal Declaration). If the house is a designated landmark or sits in a local historic district, review by the Daytona Beach Historic Preservation Board comes first.

Demolition permit steps in Daytona Beach
Step 1
If the building is a local historic site or a contributing structure in a local historic district, obtain a Major Certificate of Appropriateness from the Historic Preservation Board first (LDC Sec. 6.18.C.4).
Step 2
Notify Teco Peoples Gas and have gas disconnected; the gas disconnect number must be on the application before the permit is issued.
Step 3
Notify FPL and have power disconnected.
Step 4
If there is a septic tank, obtain a Volusia County Environmental Health septic tank abandonment permit.
Step 5
Record the Notice of Commencement.
Step 6
Submit the completed checklist, notarized application and signed Notice of City Utilities Removal Declaration.
Step 7
City staff remove the water service before work begins; the sewer lateral is capped at the property line.
Step 8
Demolish, remove all materials and restore the site per LDC Sec. 6.18, then pass the demolition final inspection.
Documents Daytona Beach asks for
| Document | What it is |
|---|---|
| Completed demolition permit application | Notarized affidavit; includes asbestos notification statement. [1] |
| Signed Notice of Utilities Removal Declaration | [1] |
| FDEP Notice of Asbestos Renovation or Demolition | If applicable. Application states notification under 62-257.301, F.A.C. may be required even if no asbestos is present. [1] |
| Owner approval to demolish | If applicable. [1] |
| Recorded Notice of Commencement | [1] |
| Gas disconnect | Teco Peoples Gas notified and gas disconnected; gas disconnect number and issuing person on application. [1] |
| Power disconnect | Florida Power and Light notified and power disconnected. [1] |
| Septic tank abandonment permit | Volusia County Environmental Health, if applicable. [1] |
| Pre-demolition as-built survey | Required if construction of a single family structure is anticipated. Rebuilding a non-conforming single family structure must stay within the original footprint (LDC 8.3.e.1.c). [1] |
| Impact fee credit documentation | To claim impact fee exemptions for new construction, square footage and plumbing fixture units must be documented and verified by city staff. [1] |
| Asbestos survey | If required. [1] |
If the house is historic in Daytona Beach
Who reviews it: Daytona Beach Historic Preservation Board.
When it applies
- Demolition of a building, structure or object listed individually on the local register of historic places.
- Demolition of a building in a historic district on the local register that is classified as contributing to that district.
- Any demolition within a Historic Overlay (HO) district must comply with a Certificate of Appropriateness (LDC Sec. 6.18.B).
How the review works
- Demolition requires a Major Certificate of Appropriateness (LDC Sec. 3.4.J).
- Pre-application staff conference; neighborhood meeting optional.
- Staff report, then a quasi-judicial public hearing scheduled within 60 days after a complete application.
- Historic Preservation Board makes the final decision; it may approve subject to a demolition delay.
- The Site Demolition and Restoration Permit is approved only if any required Certificate of Appropriateness has been obtained (LDC Sec. 3.4.O).
What the board can ask for
- Before the city issues the permit after a delay, architectural and historic documentation must be prepared by the applicant and submitted (LDC Sec. 3.4.J.3.i(d)).
- With owner consent the Board may request recording of architectural details by photographs, documents and scaled drawings.
- Undue economic hardship claims may include two written cost estimates; a structural soundness report from a licensed engineer, contractor or architect experienced in rehabilitation; market value now, after demolition and after renovation; a rehabilitation feasibility estimate; purchase price, date and seller with any relationship and financing terms; two years of income, expenses and cash flow (LDC Sec. 3.4.J.6).
Demolition delay: Up to six months, based on historic significance and the time needed to arrange an alternative; after the delay and documentation the city issues the permit on demand if other requirements are met (LDC Sec. 3.4.J.3.i).
Relocation, salvage and donation: During a delay the Board may consult community groups, recommend acquisition, and explore moving the structure. With the owner's consent it may ask the owner to salvage specified building materials, architectural details, ornaments and fixtures for reuse in other historic properties, or the Board or an interested party may salvage them at its own expense (LDC Sec. 3.4.J.3.i).
Utilities, asbestos, septic and trees in Daytona Beach
The office that issues it
State rules apply on top of the local ones
The asbestos notice, septic and well abandonment, owner-builder limits and the Notice of Commencement come from state law. See the Florida rules that apply to every demolition.
Straight answers
Do I need a permit to demolish a house in Daytona Beach?
Yes. Residential demolition in Daytona Beach is permitted through the City of Daytona Beach (Site Demolition and Restoration Permit under LDC Sec. 3.4.O plus demolition building permit).
Who can pull a demolition permit in Daytona Beach?
Contractor, authorized agent, or owner signs the checklist; the application includes a notarized Owner's/Permit Applicant Affidavit and contractor license number.
What if my house is historic in Daytona Beach?
If the house is a local landmark or in a local historic district, Daytona Beach Historic Preservation Board reviews the demolition before a permit can issue. Up to six months, based on historic significance and the time needed to arrange an alternative; after the delay and documentation the city issues the permit on demand if other requirements are met (LDC Sec. 3.4.J.3.i).
Do I need an asbestos survey to demolish a house in Daytona Beach?
Application statement: notification to FDEP under Chapter 62-257.301, F.A.C. may be required prior to demolition even if no asbestos is present; applicant affirms compliance with Chapter 62-257, F.A.C. and 40 CFR 61.140 to 61.157.
Can Brightview handle the demolition in Daytona Beach?
Yes. Brightview Homes (CRC1334100) pulls the permit under its Florida contractor license and runs the asbestos survey and notice, utility disconnects, historic documentation when it applies, tear-down, haul-off and final inspection. Demolition is quoted per job, typically $12,000 to $24,000.
Where this comes from
Every fact on this page comes from the official sources below, read on the date shown. Rules change; the building department has the final word.
- Daytona Beach Demolition Permit Package 2020 (includes LDC Sec. 6.18)
https://daytonabeach.gov/DocumentCenter/View/18559/Demolition-Permit-Package-2020 - Daytona Beach LDC Sec. 3.4, Application specific procedures (Municode)
https://library.municode.com/fl/daytona_beach/codes/land_development_code?nodeId=DABELADECO_ART3REPR_S3.4APPEPR - FDEP Homeowner's Guide to the CCCL Program
https://floridadep.gov/sites/default/files/Homeowner's%20Guide%20to%20the%20CCCL%20Program%206_2012%20(002)_0.pdf
What we could not confirm in published sources
Ask the building department about these before you plan around them.
- Demolition and Site Demolition and Restoration Permit fees.
- Major Certificate of Appropriateness fee.
- Current online permit portal for demolition submittals.
- Names and map of Daytona Beach local historic districts (Historic Overlay).
Get this scope quoted in Volusia County
Send the address or parcel ID. A real person replies within one business day with a written proposal. Nothing is ordered and nothing is charged until you approve it.
Prefer Spanish? Our team works with you in English or Spanish, from the county board to the permit counter.
- Residential Demolition