Demolition permit guide · Lake County

How to demolish a house in Groveland, FL

In Groveland, residential demolition permits are issued by the City of Groveland Building Department (application: Demolition Permit Packet (Demolition Checklist plus Permit Application, revised 12/2023)).

Verified 2026-10-12 from 4 official sources
Residential lot
CRC13341008 Central Florida counties480 N Orlando Ave, Suite 236, Winter Park, FL 32789(407) 543-1739
The process

Demolition permit steps in Groveland

  1. Step 1

    Disconnect all utilities before demolishing.

  2. Step 2

    If there is a septic tank, have it pumped, crushed and backfilled with clean compacted fill, and get a certificate from a licensed septic contractor.

  3. Step 3

    Submit the application, property record card, site plan, Notice of Commencement if the job is over $5,000, and owner/builder affidavit if applicable, through eTRAKiT or by email to PERMITTING@GROVELAND-FL.GOV.

  4. Step 4

    Schedule inspections in eTRAKiT.

What to submit

Documents Groveland asks for

DocumentWhat it is
ApplicationGroveland permit application with Demolition selected. [2]
Property Record CardListed on the demolition checklist. [2]
Notice of CommencementIf job value is over $5,000. [2]
Owner/Builder AffidavitIf applicable. [2]
Site PlanListed on the demolition checklist. [2]
Septic contractor certificateIf a septic tank is present. [2]
Before the machine shows up

Utilities, asbestos, septic and trees in Groveland

Utilities
  • All utilities: All utilities must be disconnected before demolishing the building. [2]
Asbestos

FDEP: Commercial buildings: asbestos certification must be submitted to FDEP, with a copy provided with the permit application. [2]

Septic and well

Licensed septic contractor (city checklist); DOH-Lake not named: Septic tank must be pumped, crushed and backfilled with clean compacted fill before demolition; provide certificate from a licensed septic contractor. [2]

Good to know
  • Fee schedule note: fees are double in the Green Swamp (footnote on the August 2025 schedule; confirm whether it applies to demolition).
Where to file

The office that issues it

City of Groveland Building Department

Department website

eTRAKiT

Demolition application

Who may apply: Licensed contractor or owner-builder; packet includes the state Owner Builder Disclosure Statement.

Fee: Fee schedule (August 2025): Residential Demolition $100.00; Commercial Demolition $200.00; work started before permit issuance is double the permit fees.

Florida rules

State rules apply on top of the local ones

The asbestos notice, septic and well abandonment, owner-builder limits and the Notice of Commencement come from state law. See the Florida rules that apply to every demolition.

Questions people actually ask

Straight answers

Do I need a permit to demolish a house in Groveland?

Yes. Residential demolition in Groveland is permitted through the City of Groveland Building Department. Fee: Fee schedule (August 2025): Residential Demolition $100.00; Commercial Demolition $200.00; work started before permit issuance is double the permit fees..

Who can pull a demolition permit in Groveland?

Licensed contractor or owner-builder; packet includes the state Owner Builder Disclosure Statement.

Do I need an asbestos survey to demolish a house in Groveland?

Commercial buildings: asbestos certification must be submitted to FDEP, with a copy provided with the permit application.

Can Brightview handle the demolition in Groveland?

Yes. Brightview Homes (CRC1334100) pulls the permit under its Florida contractor license and runs the asbestos survey and notice, utility disconnects, historic documentation when it applies, tear-down, haul-off and final inspection. Demolition is quoted per job, typically $12,000 to $24,000.

Sources · verified 2026-10-12

Where this comes from

Every fact on this page comes from the official sources below, read on the date shown. Rules change; the building department has the final word.

  1. Groveland Applications and Forms
    https://www.groveland-fl.gov/132/Applications-Forms
  2. Groveland Demolition Permit Packet (rev. 12/2023)
    https://groveland-fl.gov/DocumentCenter/View/6677/Demolition-Permit-Packetpdf
  3. Groveland Updated Fee Schedule (Aug 2025)
    https://groveland-fl.gov/DocumentCenter/View/7934/UPDATED-FEE-SCHEDULE-1?bidId=
  4. https://gvld-trk.aspgov.com/etrakit/
    https://gvld-trk.aspgov.com/etrakit/

What we could not confirm in published sources

Ask the building department about these before you plan around them.

  • Building Department phone and street address not read on an official page.
  • No historic preservation program found or confirmed absent.
  • Whether the Green Swamp double-fee footnote applies to demolition fees.
Start here

Get this scope quoted in Lake County

Send the address or parcel ID. A real person replies within one business day with a written proposal. Nothing is ordered and nothing is charged until you approve it.

Prefer Spanish? Our team works with you in English or Spanish, from the county board to the permit counter.

Selected scope
  • Residential Demolition
What is the plan? *